Studies, Business Case Evaluation

Pembroke Resources – Olive Downs Complex

Pembroke Resources
Project Description

Flagstaff undertook the management of multiple integrated feasibility studies:

  • Major Mine Expansion Study: Duplication of processes and non-process infrastructure to double production
  • CPP Debottlenecking Study: optimising existing CPP performance to achieve ~20% throughput increase
  • Tailings Management Study: Optimise the tailings management strategy and infrastructure to support production while minimising CAPEX and OPEX
  • Scope: Development of technical solutions, definitive scopes, execution plans, and budgets for FID approval to increase CHPP production from
    6Mtpa to 14.4Mtpa
Project Details

Client: Pembroke Resources

Pembroke Resources is an Australian based company focused on development of high-quality steelmaking coal assets.

Sector: Resources

The Challenge

Complex Multi-Study Programme

  • Immature organisational systems and capability to support the development of a major projects portfolio
  • Each project within the portfolio required development of functional solutions, scope definition, and Class 3 estimates for production expansion with tight FID timelines
  • Multiple interfaces, stakeholders, constraints and conditions across the portfolio, operations, community, and statutory authorities.
  • Coordination of multiple Engineering Service Providers
  • Tailings management strategy required immediate

The Outcome

  • Negotiated EPC contractor relationships and managed multiple engineering service providers to deliver integrated technical solutions.
  • Studies delivered under budget to Class 3 maturity to enable FID approval with confidence in technical solution, cost, schedule, and execution capability – enabling a pathway to double production capacity.
  • Value Enhancement: Business case optimised and expedited with the identification of an interim debottlenecking upgrade
  • Integrated Systems Approach: Deployed proven project management systems for complex multi-study delivery
  • Cost Performance: Study portfolio delivered 20% under budget
  • Risk Mitigation: Strategic tailings solution eliminated significant capital investment in the near term
  • Execution Ready: Project positioned through planning, maturity of solution and systems and processes for immediate transition to execution