Project Description

New malting plant for Barrett Burston Malting (subsidiary of GrainCorp). First plant to be built in Queensland in 40 years. Facilities included:

  • Barley receiving and storage
  • Barley cleaning and handling
  • Steeping
  • Germination of Barley
  • Kiln
  • Malt cleaning, handling and storage
  • Malt truck loading
  • Refrigeration Plant
  • Weighbridges
  • Site drainage, road works
Project Details

Client: Built Environs

The Challenge

  • Built Environs (BEPL) undertook the project as a lump sum turn-key (LSTK) contract
  • BEPL had limited experience in LSTK process
  • Design spread across 4 states and 5 primary designers plus an international technology provider
  • Brownfield site on an existing GrainCorp facility
Pinkenba 2

The Outcome

  • Called in to manage design completion
  • Routinely monitored design progress and targeted key packages
  • Implemented interface management across the multiple design organisations
  • Formalised cross function design review
  • Conducted design review and issues meetings with BBM representative
  • Supported BEPL with mentoring and assistance to the Project Manager
  • Enhanced document control procedures
  • Co-ordinated the site project engineering team